Working on behalf of Fulcrum we completed a connection to a 6" MP (medium pressure) gas main at a depth of 6 meters. In addition we laid 180mm PE pipe to a governor house, to feed the Thames Water Treatment plant.

The design for the deep excavation was carried out by MGF Designs, they also designed the dig box and delivered it to site which enabled the work to be carried out.