Jaguar & Land Rover, Coventry

Project Type

New Gas Connection
Directional Drilling
Project Management

The Client

Energy Assets

Methods Used

Directional Drilling
Inset Tee Connection

Technical Data

Medium Pressure
3.6 KM x 180mm MDPE

Project description

We were required to supply Jaguar Land Rover with a new medium pressure gas connection, to feed the planned expansion of their global head quarters. The project was started at the start of 2016 and completed ahead of schedule. The chosen lay method for this project was Directional Drilling which assisted in laying the pipe under brookes and in difficult areas that typical methods would not of been able to achieve.